CPM Coordination of Baseline Construction Project Schedules

In my day-to-day work as a scheduler, I interface with all sorts of construction professionals. I have found that the degree to which they understand the technical and theoretical subtleties of CPM CPM Coordination of baseline scheduling varies widely. One might expect project managers with larger contractors to have more experience than smaller ones, but I find that not always to be so. In the end, they really don’t need many technical skills to be key to the schedule management plan; just good insight and vision of the project.

Insofar as coordinating baseline construction project schedules with contractors and their project managers, I prefer CPM baseline backup from each major or critical-path subcontractor or vendor, including cost and resource loading. That would be in a perfect world. Most don’t have the wherewithal to create a schedule in a scheduling platform, however, I have found that this information can be conveyed in any number of ways – so long as the timeline is accurate, and then incorporated into the master schedule. Good project managers make for the best schedulers.

Some contractors believe that the scheduler works in a vacuum: that he reviews the drawings, develops his estimates according to his own interpretations of available resources and production rates, and develops his schedule based on this limited input. This is a low-level misunderstanding that is quickly dispelled by the notion that it is the opposite; that the contractor tells the scheduler how he sees the project timeline enfolding, and the scheduler then develops the CPM baseline schedule.

It is therefore critical that the project manager understands that he is central to the data gathering process that facilitates the building of the schedule. Thus, let the project manager know on day 1 of his required level of contribution and participation, and the project manager in turn must alert his subcontractors and vendors of their requirements.

When schedulers require, or at least insist on it, contractors are reliant on their subcontractors and vendors to confirm duration, fabrication windows, and delivery dates. Schedulers require certain data, but not all schedulers know they require it, and don’t know to ask. For example, if a custom generator was to be installed for a project, many schedulers might guess at fabrication time, rather than get a hard-date from the supplier. If the generator should wind up in the critical path …

When it comes to subcontractors, scheduling without their input can be a slippery slope. For instance, a scheduler could not guess at duration without knowing a given contractor’s resources and production rates. Yet, he must often do so, if for instance some of the major contracts are not let before the schedule is due. Invariably, he will experience some margin of error that the subcontractor will correct him on, that will necessitate his amending of the schedule effectively, double-entry. This circumstance should always be expected when not all subcontracts are let.

Finally, the scheduler must let the project team know that

  • The creation and maintaining of the schedule is a collaborative effort, and that each player is responsible for his participation and contribution.
  • When subcontractors and vendors don’t provide timely, sufficient, or accurate back-up, the scheduler must make certain assumptions based on his best guesses
  • When schedulers make assumptions, they often use ‘place-holder’ dates to represent their best guess. These dates must be certified before the baseline is maintained.
  • Place-holder dates effectively necessitate costly time-consuming resequencing, or double-entry, thus, the fewer the scheduler uses the better for all concerned.

Archives: 2014 - 2024

Resource Loaded CPM Scheduling Strategies

Resource loaded CPM scheduling pertains to developing schedules based on activity durations predicated on production rates and constraints of available personnel or resources. Many project...

On the Adoption of AI Construction Scheduling Platforms

Recently, there have been some exciting developments in the field of AI construction scheduling platforms – such as the generative  “optioneering” platform offered by Alice Technologies*: the...

The Politics of CPM Scheduling

I think of politics in CPM scheduling primarily as an apt euphemism for sleight of hand reporting and representation of what contractors are either incapable of, or unwilling to give, accurate and...

Construction Disruption Claims & How to Optimize Them

In comparison to delay claims, construction disruption claims are a slippery slope when it comes time to make a claim. That’s because delays have finite start and end dates, where there is no work...

MEP Coordination Strategies

It’s been almost 10 years since I published my 4 part series on MEP coordination, and I thought “what better way to commemorate the occasion than with an update.” In that time a lot has changed and a...

CPM Schedule Oversight Best Strategies

CPM schedule oversight is a concern of both contractors and stakeholders.  Contractors should know what to expect from oversight consultants when they submit their schedules for approval. It...

CPM Schedule Specifications & Requirements: are they a waste of paper?

CPM Schedule Specifications & Requirements are generally found in CSI division 01 32 00 Construction Progress Documentation of a project manual or specifications, where they are routinely ignored...

Construction Completion Schedules for Accurate Closeout

  Nothing quite resembles the mad scramble contractors do to close out the final segments of their projects. By this time, the project schedule has likely been deprecated into a chaotic parallel...

Construction Bid Schedules: What They Are and Why Contractors Should Use Them

In requests for pricing (RFPs) or invitations for bids (ITBs) there are a number of requests or requirements that typically fall under the radar. One such is a seldom observed request generally known...