RepOne Consulting
CPM Scheduling | Construction Expert

cost loading

CPM Schedule Cost Loading: 10 Reasons it is Seldom Implemented

Cost loading in Primavera simply  doesn’t cut the mustard because it has so little operability to incorporate variances.

CPM Schedule Cost Loading has always been the bane of the scheduler’s existence. So much so  that schedulers – including this scheduler, routinely exclude cost loading requirements for their assignments. Exclusion of cost loading is so commonplace that GCs, CMs, and stakeholders accept it as a fact of life.

It’s no fault of experienced CPM schedulers that cost loading is not well mainstreamed, rather the fault lies with the industry and its parsimonious investment in training that makes us less productive than peer countries.

There are a number of reasons why a contractor or scheduler may exclude both resource and cost loading requirements

  1. Proper resource and cost loading go together – you can’t have one without the other. If you are missing data in either or both tables, your reports will not calculate properly.
  2. Contractors and estimators routinely estimate duration in standard units: months, weeks, days, and less frequently, fractions of days. Such estimates are not informed by calculated rates of production that can facilitate accurate resource and cost loading.
  3. Schedulers who can expeditiously draft proper cost and resource loading are the exception. All others struggle mightily, and require resources that few are willing to adequately finance.
  4. CPM training programs don’t focus on resource and cost loading, nor do they require working knowledge of one in order to become certified.
  5. Schedulers who have no construction or field experience are completely reliant on estimators’ labor and material rates and units to populate resource and cost loading data. Often, they are not privy to it, or more often: it may simply not exist. Even a scheduler with construction field experience can be quite challenged.
  6. The paucity of scheduling programs with adequate or better resource and cost loading modules is an inhibitor to adoption.
  7. P6 seems to be the go-to program for resource and cost loading; however, given the complexity and clunkiness of Primavera 6 resource and cost loading modules: they are difficult to learn and implement.Moreover, I see no development in these modules from Oracle. P6 is not the resource and cost loading I would choose Cobra, or Spider.
  8. Resource and cost loading efforts can easily be disrupted or scuttled when input data is variable or inconsistent (see comment re production rates).
  9. P6 resource and cost loading do not provide enough operability to drill down on critical aspects, such as variable production rates, and the complication between duration based and physical % based activities.
  10. The cost summaries generated by P6 are seldom  in lock-step with payment applications. Accordingly, a double-entry recording system is created (P6 and Accounting), where the P6 cost summary is manually entered so that it is consistent with payment applications.

Of course, there are public projects in which there is no option but to produce the resource and cost loading reports. In such circumstances there are two avenues from which to choose in order to achieve the same outcome. It will be self-evident which is the preferred choice of most schedulers

Proper CPM Resource and Cost Loading Requirements

A. Labor rates

B. Rates of production

C. Material unit cost

ABC, simple as it were, couldn’t be more elusive to most of us; especially those who toil with P6. To carry out the report, we must create and assign “Resources,” and “Resource Assignments.” Progress in the cost charts will be a factor of “physical %complete,” whereas in the GANTT chart, they are duration based. If there is a compendium of activities and resources that all must be manually researched and input, the outgo can be prohibitive.

This additional quandary of dealing with inconsistent progress % types is enough to induce anyone to resort to the manual, or “tweak,” method. The tweak method has the added benefit of aligning the cost tables with payment applications.

In tweaking resource and cost loading, we are no longer, in fact, implementing proper  resource and cost loading. Not to worry, the end product is the focus here. If we need the GANNT and cost summaries to align, me must:

  1. Calibrate resource assignments in days.
  2. Assign a rate of $1./hr to all activities

3. -et voila!, you have your resources assigned to a cost-loaded schedule.

However, you will note the discrepancy in the “physical % complete,” v. duration % complete,” v. Schedule % complete.

If you think this operation will bugger your EVM you’re spot on. These cost tables were merely jury-rigged to match the payment application. In other words, a scheduler and reviewer can work in consort to produce a document that resembles proper resource and cost loading, if it is in the service of mollifying stakeholders, no one is going to have a problem with that except for the most fastidious regulators. It is a wag-the-dog workaround that is often inevitable; however, a scheduler should never initiate unilaterally – only raise the issue.

 

Derek Graham

CPM Scheduler | Defect & Delay Claim Specialist | Expert Witness, at RepOne

  • 125 articles
0 comments

Archives: 2014 - 2024

Resource Loaded CPM Scheduling Strategies

Resource loaded CPM scheduling pertains to developing schedules based on activity durations predicated on production rates and constraints of available personnel or resources. Many project...

On the Adoption of AI Construction Scheduling Platforms

Recently, there have been some exciting developments in the field of AI construction scheduling platforms – such as the generative  “optioneering” platform offered by Alice Technologies*: the...

The Politics of CPM Scheduling

I think of politics in CPM scheduling primarily as an apt euphemism for sleight of hand reporting and representation of what contractors are either incapable of, or unwilling to give, accurate and...

Construction Disruption Claims & How to Optimize Them

In comparison to delay claims, construction disruption claims are a slippery slope when it comes time to make a claim. That’s because delays have finite start and end dates, where there is no work...

MEP Coordination Strategies

It’s been almost 10 years since I published my 4 part series on MEP coordination, and I thought “what better way to commemorate the occasion than with an update.” In that time a lot has changed and a...

CPM Schedule Oversight Best Strategies

CPM schedule oversight is a concern of both contractors and stakeholders.  Contractors should know what to expect from oversight consultants when they submit their schedules for approval. It...

CPM Schedule Specifications & Requirements: are they a waste of paper?

CPM Schedule Specifications & Requirements are generally found in CSI division 01 32 00 Construction Progress Documentation of a project manual or specifications, where they are routinely ignored...

Construction Completion Schedules for Accurate Closeout

  Nothing quite resembles the mad scramble contractors do to close out the final segments of their projects. By this time, the project schedule has likely been deprecated into a chaotic parallel...

Construction Bid Schedules: What They Are and Why Contractors Should Use Them

In requests for pricing (RFPs) or invitations for bids (ITBs) there are a number of requests or requirements that typically fall under the radar. One such is a seldom observed request generally known...