RepOne Consulting
CPM Scheduling | Construction Expert

construction scheduling strategies

10 Construction Scheduling Strategies Every Scheduler Should Know

Construction Scheduling Strategies: Tricks of the Trade

Every scheduler has his own intuition regarding construction scheduling strategies. However; intuition will only get you so far in the real construction world. In the field is an entirely different matter. Perhaps that is why few mechanics ever even look at a schedule. Here are some insights from a seasoned field mechanic – yours’ truly, that will help you optimize your approach to sequencing.

  1. Any construction schedule that has the luxury of finish-to-start relationships throughout is too good to be true. Always assume there will be start-to-start lag whenever possible. This is a strategy to combat over-aggressive deadlines.
  2. When calculating excavated excess fill to be hauled off-site, factor for loose fill, which will be substantially more: for example 100CY of compacted or undisturbed fill may become 130CY of loose fill to haul. Read this post for some interesting tips.
  3. Do check the boring logs, as they affect the rate of excavation, as well as noting areas of rock, or those requiring remediation.
  4. Painting typically is given a start-to start relationship with its immediate successors, such as electrical devices and plumbing fixtures. Devices such as fire strobes and audible alerts need to be installed, tested, and programmed – a notoriously time consuming process, which is often delayed by painting. Given that knowledge, when float is tight, it makes sense to install your devices and fixtures before painting. Painters can mask, and cut-in around the devices, thereby foregoing delay.
  5. Wet-work and wood don’t mix: never have wood flooring or architectural woodwork on-site unless:
    1. All wet-plaster work in the vicinity is cured, and
    2. An environmentally stable installation space is provided.
  6. Integrating new fire alarm points into an existing system is always fraught with complications. Always allow at least 1/3 extra time to commission and program the system.
  7. Familiarize yourself with the various control packages. Determine if a systems integrator will be required, and provide the necessary duration for the integration work. Systems integration is an activity overlooked far too often in construction scheduling.
  8. Never trust the productivity rates in RS Means, and similar publications for your constrcution scheduling. They are only meant to represent an average rate, for an average installation. For example, RSM might allow x hours to frame a 100LF run straight partition, yet if there were 10 inside and 10 outside corners, partitions would be factored at the same rate, although productivity might be only 50% of a straight run.
  9. Understand the hierarchy of the MEP installations. Basically, ‘tin-wins,’ i.e., sheet metal duct work is installed high and tight, followed by plumbing, electric, and sprinkler heads at the bottom. This hierarchy is a factor of access: anything installed above the ceiling before the duct will obstruct it.
  10. Include separate activities for lag. Otherwise, end-user may not fully understand your sequencing. Moreover, many agencies won’t allow lag, unless you show them as such separate activities.
  11. Bonus point: check the specifications for required controlled testing, such as duct and sprinkler pressure tests, which can delay the closing of your ceilings, and add activities for them.

These construction scheduling strategies should help shape up any build-out timeline.

Happy Scheduling!

more on this topic

Archives: 2014 - 2024

Resource Loaded CPM Scheduling Strategies

Resource loaded CPM scheduling pertains to developing schedules based on activity durations predicated on production rates and constraints of available personnel or resources. Many project...

On the Adoption of AI Construction Scheduling Platforms

Recently, there have been some exciting developments in the field of AI construction scheduling platforms – such as the generative  “optioneering” platform offered by Alice Technologies*: the...

The Politics of CPM Scheduling

I think of politics in CPM scheduling primarily as an apt euphemism for sleight of hand reporting and representation of what contractors are either incapable of, or unwilling to give, accurate and...

Construction Disruption Claims & How to Optimize Them

In comparison to delay claims, construction disruption claims are a slippery slope when it comes time to make a claim. That’s because delays have finite start and end dates, where there is no work...

MEP Coordination Strategies

It’s been almost 10 years since I published my 4 part series on MEP coordination, and I thought “what better way to commemorate the occasion than with an update.” In that time a lot has changed and a...

CPM Schedule Oversight Best Strategies

CPM schedule oversight is a concern of both contractors and stakeholders.  Contractors should know what to expect from oversight consultants when they submit their schedules for approval. It...

CPM Schedule Specifications & Requirements: are they a waste of paper?

CPM Schedule Specifications & Requirements are generally found in CSI division 01 32 00 Construction Progress Documentation of a project manual or specifications, where they are routinely ignored...

Construction Completion Schedules for Accurate Closeout

  Nothing quite resembles the mad scramble contractors do to close out the final segments of their projects. By this time, the project schedule has likely been deprecated into a chaotic parallel...

Construction Bid Schedules: What They Are and Why Contractors Should Use Them

In requests for pricing (RFPs) or invitations for bids (ITBs) there are a number of requests or requirements that typically fall under the radar. One such is a seldom observed request generally known...