RepOne Consulting
CPM Scheduling | Construction Expert

duct shop drawings

Part 2/4, MEP Coordination: Example of Shop Drawings and Detailing

A good example of an installation that typically requires shop drawing preparation and submittals would be galvanized steel duct-work distribution for a forced air system, which is a sub-component of many heating-ventilation-air-conditioning (HVAC) designs. Such a system must be properly dimensioned, detailed, and depicted not only in itself, but in relation to adjoining structure or program – typically between the floor or deck above and the finished dropped ceiling below.

First, the fabricator will generate schematics that represent the general design concept, are useful to verify constructability, and impart a general sense of material and labor needed to perform the work. These are typically based on the design drawings and pre-construction site visit. These schematics may be run by the engineer for his opinion, however, they are not always a required submittal (check the specification submittal requirements for each trade).

Subsequent to preparing schematics, the contractor may pre-submit his shop drawings for approval to the design team based on his schematics, which will have incorporated the design drawings. These drawings will show expected routing and rough dimensions of the duct system, including equipment, such as air-handlers, fan-coil units, etc. Despite claims to the contrary, ductwork can seldom be fabricated according to such preliminary submittals.

Although initial or preliminary shop drawings may not as yet be fully dimensioned, the engineer may issue approval pending final details. The reason partially dimensioned or incomplete shop drawings are often issued is to save time, as HVAC systems are usually in the critical-path of the schedule. For example, the fabricator may order his material while he awaits field dimensioning. In either case, a set of as-builts is typically issued at the completion of the work to represent the actual installation.

While duct shop drawings may be submitted for approval before dimensions can be finalized in the field, many details need to be refined before fabrication can start, such as:

  • Top and bottom of duct dimensions from finished floor – especially where duct is stacked or intersects
  • Lengths of ductwork, especially where duct sizes change or transition
  • Direct take-offs from equipment supplies and returns
  • Offsets from intersecting elements, and adjacent program and framing, some of which may not be in place
  • Dimensioning of turning radii
  • Final dimensions, including fittings and insulation that make clearances changeable

Naturally, the engineer and architect will eventually want to know this information; however, they may give partial approval to shop drawings pending final dimensions, in order to allow the fabricator to save time, or resubmit.

Another reason why it’s risky and likely ill-conceived for the contractor to fabricate before major framing elements are in place is because there is always a strong likelihood that not everything will be constructed as planned, or unforeseen or hidden conditions necessitate a change of plan. If material needs to be refabricated because it was not properly coordinated or dimensioned the contractor will be liable for the costs. This is why smart fabricators do not manufacture until they can guarantee “hold” dimensions. As ductwork is fabricated off-site, there is no way to correct mistakes in the field.

Next, we will discuss the integration of the ductwork into the rest of the program in

Part 3: MEP coordination, BIM & CAD: how do Shop Drawings fit in?

go back to

Part 1: Taking the Mystery out of Construction Shop Drawings

Archives: 2014 - 2024

Basic Architectural Millwork Scheduling

The Devil is in the Details Architectural millwork scheduling is a process describing several moving parts throughout the course of the project lifecycle, beginning with the design intent and design...

Choosing CPM Scheduling Platforms to Meet Your Needs

CPM Scheduling Platforms as Models of Efficacy Choosing CPM scheduling platforms is a matter of integrity and scale. You want to have the right tool box for the needs of your organization and the...

Generating Effective Construction Schedule Oversight Reports

Construction Schedule Oversight Success is Predicated on Having the Right Skill Sets There are both art and science at play in the business of preparing effective and productive CPM construction...

Delay and Disruption Cases: a Tale of Two Claims

I recently had the pleasure of serving as an expert on two concurrent delay and disruption cases that proved to provide some interesting insights into the nuances of delay and disruptions experienced...

Construction Schedule Acceleration: Optimizing for Success

Schedule Acceleration: The Big Squeeze Construction schedule acceleration is a strategy designed and intended to either mitigate and stanch off float erosion (delay,) or to recover lost time –...

Successful Shop Drawing and Submittal Strategies

There has always been a lot of confusion about what constitutes a ‘shop drawing,’ submittal,  and finally – coordination drawings. In order to optimize project management outcomes, it is...

Mastering Retrofit Construction Layout: Optimizing Axes Lines and Benchmarks

Retrofit construction layout is distinct from new construction in that new elements are dictated by existing program to remain or ‘ETR’ – such as structure supporting walls, floors, and...

Punch List Techniques and Strategies for General Contractors 

Confusion and lack of consensus over what a construction project punch list or punch-out list is and what it isn’t, contribute mightily to project conflict in the close out stage of most any...

Managing Construction Contract Extension of Time Claims

Very few construction projects seem to progress without at least one general disruption or delay time impact that affects schedule milestones, and requires trades to accelerate in order to keep to...