General Requirements & General Conditions: What’s the Diff?

There is persistent need for GCs and CMs to distinguish and quantify the costs of GC/GRs to their clients. This is one of the hardest sells, and clients frequently cannot access the concept. GC/GRs are not always quantified scientifically, or with any degree of exactitude, and merely are assigned a value as percentage.

As an estimator, I have seen endless permutations of GC/GRs in project documentation, as there is no standard. There being no standard, I believe it is helpful to define these typically broad terms in a simplified and specific sense, lest the discussion degenerate into the ambiguity that many GCs and CMs experience.

I find that Public & Government specifications- with their tendency to be comprehensive and unambiguous – offer a fair approximation of how the terms “General Requirements” and “General Conditions” differ, and offer a basis for study or examination. Such agencies often require iteration or detailed costs of GC/GRs in the ITB (invitation to bid). This is especially so for CM contracts. Private work specifications are notoriously wanting of clarification, and are typically the most nebulous.

In the project specifications, General Requirements tend to be specific to the owner’s needs. They are often merely conveyed as boilerplate, and tend to be immutable. General Conditions too are also conveyed as boilerplate, however, prosecution is largely up to the GC or CM. General Conditions are often referred to as “whatever it takes to get the job done.”

I predicate my views that the following pertains – for the most part – to GCs and CMs, and to a lesser extent, subcontractors. It is helpful to think of General Requirements as mostly administrative, and General Conditions as both administrative, and faciliatory.

General Requirements: defines the specific protocols for administrative programs associated with a given project, and each respective trade or division (CSI), such as submittals, scheduling req’s, LEED, payment apps, permitting, inspections, daily logs, RFIs, progress meetings and meeting minutes, and all other project documentation. They may appear in Division 0, within specific divisions, or both.

General Conditions: there are two types: Administrative and Field.

Field: (mostly manual labor) those responsibilities and activities necessary to facilitate the ‘general’ overall prosecution of the work, that are NOT otherwise iterated in the scope of work, General Requirements, or SOV, to include: general labor, house-keeping, site management (superintendent), safety measures, temporary utilities, trailers, etc.

Administrative: (non-manual labor) those responsibilities and activities necessary to facilitate the overall prosecution of the work, that are NOT otherwise iterated in the scope of work, general requirements, or SOV, to include: project manager, estimator, principals, project engineers, bookkeeping, and administrative personnel.

General Requirements and General Conditions, as they pertain to Litigation:

Invariably, construction disputes tend to focus on the ‘work proper,’ and don’t consider the value of General Requirements or General Conditions toward a given claim. I believe this is owing to the general inability of GCs and CMs to accurately represent such costs with any acceptable degree of exactitude, and the owners being unaware of their intrinsic value.

In my work as an expert witness for construction damage litigation, I sometimes suggest the quantifying of the value of General Conditions and General Requirements for contract disputes, where standard of care comes into question. After all, if GC/GRs are 5-10% of the contract value, does it not behoove one to examine the true nature of such costs?

Archives: 2014 - 2024

Basic Architectural Millwork Scheduling

The Devil is in the Details Architectural millwork scheduling is a process describing several moving parts throughout the course of the project lifecycle, beginning with the design intent and design...

Choosing CPM Scheduling Platforms to Meet Your Needs

CPM Scheduling Platforms as Models of Efficacy Choosing CPM scheduling platforms is a matter of integrity and scale. You want to have the right tool box for the needs of your organization and the...

Generating Effective Construction Schedule Oversight Reports

Construction Schedule Oversight Success is Predicated on Having the Right Skill Sets There are both art and science at play in the business of preparing effective and productive CPM construction...

Delay and Disruption Cases: a Tale of Two Claims

I recently had the pleasure of serving as an expert on two concurrent delay and disruption cases that proved to provide some interesting insights into the nuances of delay and disruptions experienced...

Construction Schedule Acceleration: Optimizing for Success

Schedule Acceleration: The Big Squeeze Construction schedule acceleration is a strategy designed and intended to either mitigate and stanch off float erosion (delay,) or to recover lost time –...

Successful Shop Drawing and Submittal Strategies

There has always been a lot of confusion about what constitutes a ‘shop drawing,’ submittal,  and finally – coordination drawings. In order to optimize project management outcomes, it is...

Mastering Retrofit Construction Layout: Optimizing Axes Lines and Benchmarks

Retrofit construction layout is distinct from new construction in that new elements are dictated by existing program to remain or ‘ETR’ – such as structure supporting walls, floors, and...

Punch List Techniques and Strategies for General Contractors 

Confusion and lack of consensus over what a construction project punch list or punch-out list is and what it isn’t, contribute mightily to project conflict in the close out stage of most any...

Managing Construction Contract Extension of Time Claims

Very few construction projects seem to progress without at least one general disruption or delay time impact that affects schedule milestones, and requires trades to accelerate in order to keep to...