RepOne Consulting
CPM Scheduling | Construction Expert

Project Drag-Down, & Construction CPM Schedule Decay

When Critical Paths Become Endangered

 

CPM Schedule Decay: It’s ugly – watching a contractor’s best laid plans slowly disintegrate into chaos over the course of months – even years. The degree of this disintegration is commensurate with the baseline schedule level of aggressivity, or deprecation of project controls. Not infrequently do an owner and builder contract to build according to overly aggressive schedules that they should know – can only portend disaster.

Savvy builders know from experience that such contract schedules are unrealistic, yet they agree to these terms every day. Why? Because they know the likelihood of design changes and change orders will inevitably make the contract schedule obsolete, inevitably affording them the slack they need to extend deadlines.

This happens so often because many daunting design challenges are met with feeble attempts by design professionals to substantially* define the work in the base (not revised) construction drawings.  Most notorious is the absence of MEP and structural pre-coordination that should take place between the designing architect and MEP and structural engineers that is meant to obviate design conflicts, or ‘clashes’. Sadly, there seems never to be enough pre-coordination, and the trades end up having to make multiple resubmittals, or issue RFIs, to resolve conflicts.

RFIs necessitating time consuming and disruptive designing on the fly is the consequence of design oversight, especially if it involves the owner. Many designers mistakenly convince themselves that they can feed’ a job with frequent revisions, or build the job from ‘sketches,’ similar to the fast-track approach, until the schedule begins to run away. Perhaps the design team expects the sub-contractors to pick up the slack.

Projects with unforeseen, or  pre-existing conditions present a particular challenge to the design and build teams to keep on schedule, as do complex projects, or those with many technical or sophisticated innovations, or finishes. A scheduler must skuffle to keep up with the continual barrage of RFIs, SWOs, and change orders for these projects, which he must integrate into the project database. If not, the schedule lapses into disarray. If the information is not forthcoming, the schedule becomes threatened, and eventually abandoned.

Some projects become side-tracked to such an extent that only a rebaselining can represent the revised critical path, and this too changes every month, just like the weather. We used to say the team were “flying by the seat of their pants.” As a scheduler, one usually can see catastrophes coming. It begins when the contractor becomes incommunicado: perhaps embroiled in the building process, he no longer returns calls or emails regarding updates, or otherwise.

Other projects become completely unmanageable, in terms of methodology, when there no longer is a linear path of progression, or there are too many, i.e., a schedule would be superfluous to represent. If an owner or contractor understands nothing else about the CPM, he knows when a scheduler will no longer avail them, or is no longer ‘needed.’ In my mind, this acknowledgement is tantamount to an utter failed effort in planning, and concedes the ability to represent disruptions in a claim schedule, or if the contract should come to arbitration or litigation.

I wonder at contractors who abandon, or otherwise let a schedule tank as a consequence of project instability. I suppose they – at some given point, became resigned to the fact that they would not be able to develop proper claim schedules to represent disruption, i.e., they accept the responsibility for the cost of such disruptions, and they do not bother to contest what they could nary challenge in any cogent fashion.

*substantial, meaning: having all the elements necessary for the builder to construct a substantially complete product.

 

Archives: 2014 - 2024

Generating Effective Construction Schedule Oversight Reports

Construction Schedule Oversight Success is Predicated on Having the Right Skill Sets There are both art and science at play in the business of preparing effective and productive CPM construction...

Delay and Disruption Cases: a Tale of Two Claims

I recently had the pleasure of serving as an expert on two concurrent delay and disruption cases that proved to provide some interesting insights into the nuances of delay and disruptions experienced...

Construction Schedule Acceleration: Optimizing for Success

Schedule Acceleration: The Big Squeeze Construction schedule acceleration is a strategy designed and intended to either mitigate and stanch off float erosion (delay,) or to recover lost time –...

Successful Shop Drawing and Submittal Strategies

There has always been a lot of confusion about what constitutes a ‘shop drawing,’ submittal,  and finally – coordination drawings. In order to optimize project management outcomes, it is...

Mastering Retrofit Construction Layout: Optimizing Axes Lines and Benchmarks

Retrofit construction layout is distinct from new construction in that new elements are dictated by existing program to remain or ‘ETR’ – such as structure supporting walls, floors, and...

Punch List Techniques and Strategies for General Contractors 

Confusion and lack of consensus over what a construction project punch list or punch-out list is and what it isn’t, contribute mightily to project conflict in the close out stage of most any...

Managing Construction Contract Extension of Time Claims

Very few construction projects seem to progress without at least one general disruption or delay time impact that affects schedule milestones, and requires trades to accelerate in order to keep to...

Architectural Alignments in Construction

In most interior fit-out, builders only need to align major or basic elements – like walls, floors, and ceilings. As the sophistication of their commissions ratchet up, these architectural...

Resource Loaded CPM Scheduling Strategies

Resource loaded CPM scheduling pertains to developing schedules based on activity durations predicated on production rates and constraints of available personnel or resources. Many project...