RepOne Consulting
CPM Scheduling | Construction Expert

schedule acceleration

Construction Schedule Acceleration: Optimizing for Success

Schedule Acceleration: The Big Squeeze

Construction schedule acceleration is a strategy designed and intended to either mitigate and stanch off float erosion (delay,) or to recover lost time – so to better control or advance completion dates. There are a number of ways contractors seek to achieve these outcomes. Some are more scientific than others.

 

Proper schedule acceleration methods rely on CPM schedules with coherent or valid critical paths. Reliable schedules can be modified without compromising integrity. Acceleration schedule logic can be no more efficient than the baselines they modify, thus it is exigent that the project has a coherent schedule. Given the low percentage of reliable schedules, valid acceleration schedules are somewhat of a rarity. This is so for a number of reasons:

 

Construction schedule acceleration proposes recovery or mitigation of lost time frames through compression in two-ways: enhancing resources, and expediting product deliveries. Typical recovery efforts merely throw additional resources at the project: ‘bomb the job,’ with the assumption that production will increase. They may seek compensation for shift work and overtime, but only when they are not at fault for delay, which is seldom the case. Otherwise, general contractors are reluctant to pay their subs for extra manpower.

 

The same is true of expediting (red-labeling) product deliveries. All too often I have seen product rushed to a site, only to be reoriented to a warehouse until such time as it is needed on the site. The contractor who owns the product will be stuck for additional transport fees, as well as storage fees.

 

Enhancing resource strategies through schedule acceleration needs to utilize reliable and feasible production rates. The availability of personnel to meet the increase must be validated: a prime’s scheduler may not unilaterally create a compressed schedule before assurance from trades and suppliers that required resources are available. This can be a challenging endeavor when there are material and manpower shortages.

 

Another consideration is the availability of space for increased manpower. Too many workers – or ‘trade stacking,’ creates congestion, reduces productivity, and enhances the likelihood of accidents. It is also a big morale stressor:

 

For example, I remember building an art gallery owner who bullied the general contractor into bombing her project in order to meet an opening date she had moved up several weeks from the contract date. The focus at the time was a  15’ x 30’ foyer with a new level-5 plaster ceiling, and array of recessed 24 or so rectangular Nulux light fixtures. The fixtures had to be dead on aligned as even the slightest misalignment would translate. Despite strings, jet-lines and constant measuring, no array ever properly aligned. The acceleration was an exercise in futility.

 

The bustling room included some 8 electricians, 2 carpenters, 2 laborers, 4 plasterers, and a scissor lift. The upshot was that the ceiling and lights were continually misaligned and needed to be reinstalled, and finally, a laborer was run into by the scissor jack. After the fiasco, the electrician sent a bill for $25K in extra labor – which as project manager I summarily discarded.

 

Other problems with trade stacking are that work is installed out of sequence with the plan, which leads to various trades not having access to their work areas when they need it. As they move around or are left standing around, their production rates begin to plummet. Out of sequence work is too often used (unwisely) as a mitigation tool. For example, if sheet metal was not ready, a super might order electricians to pull their wire before the sheetmetal is installed, creating access issues for the tin knockers, insulators, plumbers, and any trades working above the wire.

Playing for Time

Another mistake that is frequently made is when a given resource is enhanced despite acceleration of that trade having no effect on the critical path. Resources shouldn’t be enhanced without having a critical path impact. In order to assess impact, it is necessary to model ‘what if,’or ‘reflection’ schedules that provide a valid impact model. This same schedule can be used to represent a future claim by the contractor. Conversely, there’s little chance of a claim without a valid impact schedule model.

 

In some cases, the contractor’s critical path does not represent all of the owner’s milestones. Such a lack of consensus invariably leads to claims and late penalties. It is of utmost importance that ownership provides all required milestones to the contractor, and is assured they can be met before inking a contract. Otherwise, a contractor may rightly demand acceleration fees. Again, good luck with that effort.

 

As a project is bombed with manpower, fragmentation ensues from the chaos. Before long, it is no longer possible to track the schedule. This is especially true when the baseline schedule has not been modified to represent the acceleration effort. Another conundrum is the failure of the prime contractor to enhance his own labor and management resources to oversee the mess.

 

Few contractors have the luxury of a resource loaded construction schedule that can be used as a model for acceleration. This is owing to the general poor quality and faulty logic endemic to most schedules, and the failure to generate schedules based on resources and production rates. Without those, prime contractors are running blind, and trades and ownership are along for a wild ride.

 

Archives: 2014 - 2024

Basic Architectural Millwork Scheduling

The Devil is in the Details Architectural millwork scheduling is a process describing several moving parts throughout the course of the project lifecycle, beginning with the design intent and design...

Choosing CPM Scheduling Platforms to Meet Your Needs

CPM Scheduling Platforms as Models of Efficacy Choosing CPM scheduling platforms is a matter of integrity and scale. You want to have the right tool box for the needs of your organization and the...

Generating Effective Construction Schedule Oversight Reports

Construction Schedule Oversight Success is Predicated on Having the Right Skill Sets There are both art and science at play in the business of preparing effective and productive CPM construction...

Delay and Disruption Cases: a Tale of Two Claims

I recently had the pleasure of serving as an expert on two concurrent delay and disruption cases that proved to provide some interesting insights into the nuances of delay and disruptions experienced...

Construction Schedule Acceleration: Optimizing for Success

Schedule Acceleration: The Big Squeeze Construction schedule acceleration is a strategy designed and intended to either mitigate and stanch off float erosion (delay,) or to recover lost time –...

Successful Shop Drawing and Submittal Strategies

There has always been a lot of confusion about what constitutes a ‘shop drawing,’ submittal,  and finally – coordination drawings. In order to optimize project management outcomes, it is...

Mastering Retrofit Construction Layout: Optimizing Axes Lines and Benchmarks

Retrofit construction layout is distinct from new construction in that new elements are dictated by existing program to remain or ‘ETR’ – such as structure supporting walls, floors, and...

Punch List Techniques and Strategies for General Contractors 

Confusion and lack of consensus over what a construction project punch list or punch-out list is and what it isn’t, contribute mightily to project conflict in the close out stage of most any...

Managing Construction Contract Extension of Time Claims

Very few construction projects seem to progress without at least one general disruption or delay time impact that affects schedule milestones, and requires trades to accelerate in order to keep to...