P6 Scheduling for Brooklyn Battery Tunnel Rehabilitation, NY

The Brooklyn Battery Tunnel was slated for rehabilitation before Hurricane Sandy. After the storm, the tunnel was inundated with salt water, that destroyed sensitive control and monitoring systems, which are at least as sophisticated as those found in any modern skyscraper. Much of the fiber optic cabling and sensitive monitoring systems will have to be temped out, and replaced with new control systems, to include tunnel ventilation, tunnel lighting, traffic safety, drainage pumps, and communications.

The fiber optic loops in both tunnels must be established, and integrated before the rehabilitation can begin in one tube. I estimate the work may take about 4.5 years. The reason being that work is limited to 5 nightly closures of one tube at a time, and only 5 hours on-task, to account for mobilization/demobilization.

RepOne was hired to conduct P6 Scheduling services for the project. We generated the preliminary and baseline schedule, from NTP, through substantial completion.

Click here for Sample Primavera P6 Schedule

size0

hurricane-sandy-clean-up-mta

20121101Battery+Park+Bloom_BenC_0311

Archives: 2014 - 2024

Basic Architectural Millwork Scheduling

The Devil is in the Details Architectural millwork scheduling is a process describing several moving parts throughout the course of the project lifecycle, beginning with the design intent and design...

Choosing CPM Scheduling Platforms to Meet Your Needs

CPM Scheduling Platforms as Models of Efficacy Choosing CPM scheduling platforms is a matter of integrity and scale. You want to have the right tool box for the needs of your organization and the...

Generating Effective Construction Schedule Oversight Reports

Construction Schedule Oversight Success is Predicated on Having the Right Skill Sets There are both art and science at play in the business of preparing effective and productive CPM construction...

Delay and Disruption Cases: a Tale of Two Claims

I recently had the pleasure of serving as an expert on two concurrent delay and disruption cases that proved to provide some interesting insights into the nuances of delay and disruptions experienced...

Construction Schedule Acceleration: Optimizing for Success

Schedule Acceleration: The Big Squeeze Construction schedule acceleration is a strategy designed and intended to either mitigate and stanch off float erosion (delay,) or to recover lost time –...

Successful Shop Drawing and Submittal Strategies

There has always been a lot of confusion about what constitutes a ‘shop drawing,’ submittal,  and finally – coordination drawings. In order to optimize project management outcomes, it is...

Mastering Retrofit Construction Layout: Optimizing Axes Lines and Benchmarks

Retrofit construction layout is distinct from new construction in that new elements are dictated by existing program to remain or ‘ETR’ – such as structure supporting walls, floors, and...

Punch List Techniques and Strategies for General Contractors 

Confusion and lack of consensus over what a construction project punch list or punch-out list is and what it isn’t, contribute mightily to project conflict in the close out stage of most any...

Managing Construction Contract Extension of Time Claims

Very few construction projects seem to progress without at least one general disruption or delay time impact that affects schedule milestones, and requires trades to accelerate in order to keep to...