General Requirements & General Conditions: What’s the Diff?

There is persistent need for GCs and CMs to distinguish and quantify the costs of GC/GRs to their clients. This is one of the hardest sells, and clients frequently cannot access the concept. GC/GRs are not always quantified scientifically, or with any degree of exactitude, and merely are assigned a value as percentage.

As an estimator, I have seen endless permutations of GC/GRs in project documentation, as there is no standard. There being no standard, I believe it is helpful to define these typically broad terms in a simplified and specific sense, lest the discussion degenerate into the ambiguity that many GCs and CMs experience.

I find that Public & Government specifications- with their tendency to be comprehensive and unambiguous – offer a fair approximation of how the terms “General Requirements” and “General Conditions” differ, and offer a basis for study or examination. Such agencies often require iteration or detailed costs of GC/GRs in the ITB (invitation to bid). This is especially so for CM contracts. Private work specifications are notoriously wanting of clarification, and are typically the most nebulous.

In the project specifications, General Requirements tend to be specific to the owner’s needs. They are often merely conveyed as boilerplate, and tend to be immutable. General Conditions too are also conveyed as boilerplate, however, prosecution is largely up to the GC or CM. General Conditions are often referred to as “whatever it takes to get the job done.”

I predicate my views that the following pertains – for the most part – to GCs and CMs, and to a lesser extent, subcontractors. It is helpful to think of General Requirements as mostly administrative, and General Conditions as both administrative, and faciliatory.

General Requirements: defines the specific protocols for administrative programs associated with a given project, and each respective trade or division (CSI), such as submittals, scheduling req’s, LEED, payment apps, permitting, inspections, daily logs, RFIs, progress meetings and meeting minutes, and all other project documentation. They may appear in Division 0, within specific divisions, or both.

General Conditions: there are two types: Administrative and Field.

Field: (mostly manual labor) those responsibilities and activities necessary to facilitate the ‘general’ overall prosecution of the work, that are NOT otherwise iterated in the scope of work, General Requirements, or SOV, to include: general labor, house-keeping, site management (superintendent), safety measures, temporary utilities, trailers, etc.

Administrative: (non-manual labor) those responsibilities and activities necessary to facilitate the overall prosecution of the work, that are NOT otherwise iterated in the scope of work, general requirements, or SOV, to include: project manager, estimator, principals, project engineers, bookkeeping, and administrative personnel.

General Requirements and General Conditions, as they pertain to Litigation:

Invariably, construction disputes tend to focus on the ‘work proper,’ and don’t consider the value of General Requirements or General Conditions toward a given claim. I believe this is owing to the general inability of GCs and CMs to accurately represent such costs with any acceptable degree of exactitude, and the owners being unaware of their intrinsic value.

In my work as an expert witness for construction damage litigation, I sometimes suggest the quantifying of the value of General Conditions and General Requirements for contract disputes, where standard of care comes into question. After all, if GC/GRs are 5-10% of the contract value, does it not behoove one to examine the true nature of such costs?

Archives: 2014 - 2024

On the Adoption of AI Construction Scheduling Platforms

Recently, there have been some exciting developments in the field of AI construction scheduling platforms – such as the generative  “optioneering” platform offered by Alice Technologies*: the...

The Politics of CPM Scheduling

I think of politics in CPM scheduling primarily as an apt euphemism for sleight of hand reporting and representation of what contractors are either incapable of, or unwilling to give, accurate and...

Construction Disruption Claims & How to Optimize Them

In comparison to delay claims, construction disruption claims are a slippery slope when it comes time to make a claim. That’s because delays have finite start and end dates, where there is no work...

MEP Coordination Strategies

It’s been almost 10 years since I published my 4 part series on MEP coordination, and I thought “what better way to commemorate the occasion than with an update.” In that time a lot has changed and a...

CPM Schedule Oversight Best Strategies

CPM schedule oversight is a concern of both contractors and stakeholders.  Contractors should know what to expect from oversight consultants when they submit their schedules for approval. It...

CPM Schedule Specifications & Requirements: are they a waste of paper?

CPM Schedule Specifications & Requirements are generally found in CSI division 01 32 00 Construction Progress Documentation of a project manual or specifications, where they are routinely ignored...

Construction Completion Schedules for Accurate Closeout

  Nothing quite resembles the mad scramble contractors do to close out the final segments of their projects. By this time, the project schedule has likely been deprecated into a chaotic parallel...

Construction Bid Schedules: What They Are and Why Contractors Should Use Them

In requests for pricing (RFPs) or invitations for bids (ITBs) there are a number of requests or requirements that typically fall under the radar. One such is a seldom observed request generally known...

AI Generative-Design Poised to Displace 90% of all Architects and Why That May Be Good News

AI generative-design may prove to have unexpected benefits to the building industry. By improving the quality and developmental integrity of construction drawings, error and omissions will be...