CPM Schedulers: Stop Giving Away Your Primavera XERs Away! Upvote Idea 17591

Primavera xers are a liability to CPM consultants bottom line

Make Oracle develop the concept! with enough upvotes, it can happen!

Upvote Idea 17591 at and protect your livelihood.

It must be the weather or something that’s made me cranky this month – but I feel obliged to share a piece of advice with fellow colleagues, as well as my competitors: that’s right – I said advice for my competition. Sharing Primavera xers is bad for the business. By the time you finish reading this post you will full well understand why I say that.

It came to my attention the other day when a colleague working for a CM gave me a call. He works on a three-year project for which I created the baseline for the planning engineers. He knew this before I told him, because he had seen my schedule being used as a passive oversight control document by the stakeholders.

I said “that’s funny because my proposal for the follow up oversight was rejected.” In other words, rather than extending the oversight contract, the stakeholders had Shanghia’d my baseline, and used it for themselves, thereby eschewing outsource fees.

If you use Primavera 6, perhaps you can relate to this experience. Or worse, perhaps your Primavera xers. are circulating and being republished for commercial purposes without your knowledge.

That’s just the half of it. The bigger problem is this: once you allow your best work to be available to anyone  it no longer is proprietary, but lives in the public domain. Thus, anyone in possession of your best xers could learn all your best trade secrets and use them to compete against you.

One of two things will come of engineer’s use of your Primavera xers: either they will have no comments at all, or their comments will be rudimentary and uninformed.

It’s not unusual for planners to request only a baseline. Best practice dictates they should continue to keep parallel records to keep the CM honest, and these records should be maintained by industry trained professionals, not overly curious engineers. It’s also in fairness to the scheduling consultant. The baseline is the most difficult effort. If it is a good baseline, the updates will come easy. That is the reward for the scheduler that he deserves for generating a solid baseline.

Engineers just want the xer (thank you!) They aren’t trained in P6, and importing Primavera xers, but they think they can figure the program out on their own: not going to happen!

In fact, the conundrum of locking xers is nothing new – it’s always been the case. Why is it so easy to reproduce Primavera xers? It has to do with the way the program is set up with its databases, and the way it is exported – go ask Oracle. I have been speaking to the Primavera engineers at Oracle to see what sort of read-only protections or other work-arounds exist, or could be developed.

The Oracle Community features enhancement forums for ideas such as mine. With enough upvotes, they may just decide to develop a workaround. Without the votes, they will not.

Circulating open-source Primavera xers is like sending work out the door, as well as creating more competition with yourself. In a sense, we may find that we are competing with ourselves, when others have all our best trade secrets.

In the meantime – and this is my advice to all schedulers: copyright your work, and include language forbidding reproduction. The way I see it, the more loose xers there are laying around for engineers and dilettantes to fool with, the less work there will be for me, because they are stealing my work.

Upvote Idea 17591 at

Archives: 2014 - 2024

Resource Loaded CPM Scheduling Strategies

Resource loaded CPM scheduling pertains to developing schedules based on activity durations predicated on production rates and constraints of available personnel or resources. Many project...

On the Adoption of AI Construction Scheduling Platforms

Recently, there have been some exciting developments in the field of AI construction scheduling platforms – such as the generative  “optioneering” platform offered by Alice Technologies*: the...

The Politics of CPM Scheduling

I think of politics in CPM scheduling primarily as an apt euphemism for sleight of hand reporting and representation of what contractors are either incapable of, or unwilling to give, accurate and...

Construction Disruption Claims & How to Optimize Them

In comparison to delay claims, construction disruption claims are a slippery slope when it comes time to make a claim. That’s because delays have finite start and end dates, where there is no work...

MEP Coordination Strategies

It’s been almost 10 years since I published my 4 part series on MEP coordination, and I thought “what better way to commemorate the occasion than with an update.” In that time a lot has changed and a...

CPM Schedule Oversight Best Strategies

CPM schedule oversight is a concern of both contractors and stakeholders.  Contractors should know what to expect from oversight consultants when they submit their schedules for approval. It...

CPM Schedule Specifications & Requirements: are they a waste of paper?

CPM Schedule Specifications & Requirements are generally found in CSI division 01 32 00 Construction Progress Documentation of a project manual or specifications, where they are routinely ignored...

Construction Completion Schedules for Accurate Closeout

  Nothing quite resembles the mad scramble contractors do to close out the final segments of their projects. By this time, the project schedule has likely been deprecated into a chaotic parallel...

Construction Bid Schedules: What They Are and Why Contractors Should Use Them

In requests for pricing (RFPs) or invitations for bids (ITBs) there are a number of requests or requirements that typically fall under the radar. One such is a seldom observed request generally known...