Epic Failures in CPM Construction Scheduling History

Every now and then, I like to relax a little, step back and take stock of some of the more ambitious US megaprojects that have lurched around us, and compare their baseline schedules with actualized or projected (by owner) dates. The recent passage of appropriations for the Department of Homeland Security, and the GAO’s continued folly over its proposed massive DHS/NSA campus, in Southeast, Washington DC., brought to mind this comparison of epic projects.  Although never mentioned in project documentation, the NSA plans a huge data-center and “counter-intelligence” infrastrcture.

History of Ineptitude

For a little back story, the DHS was concocted in 2003, in response to 911. The consolidated headquarters solution, to provide a central campus to replace 50 or so satellite offices strewn randomly about Washington, DC, came in 2006. The former were outdated (2003) and dilapidated; some even had vermin infestations. All had over-market short-term rental contracts.

What better choice than St. Elizabeths Hospital, with its commanding views of the Potomac Valley, at the confluence of the Potomac and Anacostia Rivers? Except, that the ‘hood, Ward 8, is one of the most crime-ridden in the district (RCN17), which certainly concerns Coast Guard workers who had to commute to the way-station there ( lacks a parking lot, thus Coast Guard employees are encouraged to car-pool.) There is a large completed garage near the Coast Guard building, but that is reserved for future DHS employees, who will park their cars there, after the DHS building is completed (RCN 15).  The USCG in the thumbnail (TOP) complex resembles a military command center with green roofs (LEED Gold).

The sprawling site was originally/still known as the Government Hospital for the Insane, with its crumbling, historic frames, and rotting infrastructure that all must be meticulously restored and upgraded to LEED Gold Status. Somehow, its historical context strikes me as ironic. After fierce protests by local residents (three-year delay), costly litigation, and subsequent bullying by the Feds, it was agreed the 50 existing historic structures would be upgraded without compromising their architectural integrity and original fabric. Except, of course, the wrench in the works was that there weren’t sufficient roads to service the campus – a $100M oversight.

Some basic facts about the project

  • The original budget of $3.5B was revised to $4.5B. The agency cited “cost-escalation, and design changes.”
  • The original schedule of 9 years was revised to 26 years, earliest
  • Per DHS Majority of buildings are pursuing LEED 2009 Gold certification

Greatest Follies in Major Local & Fed Construction Scheduling & Planning

The 2011 schedule, below, susbsequently was pushed back a minimum of 6 years:

After years of dicckering around, the administrations masterplan petered out for real. Imagine if you overlaid the actual dates onto the DHS masterschedule below – bar-stack waterfall (slope of the furthest right end of bars stcaked) would more resemble high-tide at Cape Cod, and then add 7 years to that . The team expected to hit the ground running in FY11, and ride the wave into FY20. But the project foundered under the weight of weak leadership, and a poor site selection, and is likely to be scuttled altogether by the next change in administration.

construction scheduling

Some $1.5B has been appropriated for the project, yet only a single structure serving the US Coast Guard, with only a 50 seat snack shop to boast, has been put into service. Wherefore the rest of the expenditure? I daresay in D&D, and development of the St. Elizabeths website, which has all project documentation in its archives.

How DHS St. Elizabeths stacks up

construction schedules

Needless to say, the project is very unpopular with everyone in Washington, and may very well be scuttled altogether. In 2011, on a whim, then-Secretary of Homeland Security Janet Napolitano indicated that St. Elizabeths “may no longer be the priority at DHS,” (“DHS St. E’s to be victim of budget axe.” Jason Miller and Julia Ziegler, Federal News Radio, September 8, 2011.

Perhaps Napolitano was more concerned with border patrol financing or maybe she was too tired of the glacial rate of progress, but she let it continue its death-spiral anyway.  Nonetheless, two-years later, she requested another $93M, before an Appropriations subcommittee. Understood, as is the fashion nowadays in Washington: all of a sudden the focus is cyberterrorism.

However; I stray here, or not at least until you compare the project to other long-term epic projects, and notice that it has the highest (65%) slippage rate, below:

Long-haul Projects

If we pit the biggest losers against each other, we begin to see a pattern of gross  incompetence and absence of leadership that more often than not has only to blame the politicians who orchestrated these follies.

construction scheduling                          SAS: Second Avenue Subway, NY, NY,   ESA: East Side Access, NY, NY

Indeed, the DHS construction scheduling and planning escapade eclipses its once-thought more-infamous betters, thus making it the most epic dysfunctional master schedule ever drafted in this country. However; to its credit, it did not take the epic budget excess prize (can anyone guess which?). It makes me wonder if any CPM timelines were ever generated for these projects, or were there insufficient budget resources. If there were schedulers, did they take the fall? On some of these projects, schedulers were certainly expendable. Several of the above projects scrubbed their construction scheduling teams at least once.

I dont’ know about you, but it seems like the Fed takes a fairly cavalier and irresponsible approach to managing its construction mega-projects. To be sure, CPM scheduling is an afterthought, or may not even be implemented at all.  Nor do I find solace in the notion that the DHS St. Elizabeths is nothing more than a tax-payer funded sink-hole for an ill-conceived domestic spy agency.


Resources: RCN “Reality Check Needed: Rising Costs and Delays in Construction of New DHS Headquarters at St. Elizabeths,” U.S. House of Representatives, Committee on Homeland Security January, 2014

Other resources, and further reading

http://www.stelizabethsdevelopment.com/master-plan.html (masterplan)

http://www.govexec.com/oversight/2014/09/will-congress-pull-plug-homeland-securitys-move-st-elizabeths/94643/


 

 answer to the question

overbudgetr Fed construction projects

 

 

 

 

 

 

 

 

Yes, at a whopping 868% overbudget, the Big Dig takes the prize hands-down. The largest highway project ever, also had the highest rate of overage.

Archives: 2014 - 2024

Resource Loaded CPM Scheduling Strategies

Resource loaded CPM scheduling pertains to developing schedules based on activity durations predicated on production rates and constraints of available personnel or resources. Many project...

On the Adoption of AI Construction Scheduling Platforms

Recently, there have been some exciting developments in the field of AI construction scheduling platforms – such as the generative  “optioneering” platform offered by Alice Technologies*: the...

The Politics of CPM Scheduling

I think of politics in CPM scheduling primarily as an apt euphemism for sleight of hand reporting and representation of what contractors are either incapable of, or unwilling to give, accurate and...

Construction Disruption Claims & How to Optimize Them

In comparison to delay claims, construction disruption claims are a slippery slope when it comes time to make a claim. That’s because delays have finite start and end dates, where there is no work...

MEP Coordination Strategies

It’s been almost 10 years since I published my 4 part series on MEP coordination, and I thought “what better way to commemorate the occasion than with an update.” In that time a lot has changed and a...

CPM Schedule Oversight Best Strategies

CPM schedule oversight is a concern of both contractors and stakeholders.  Contractors should know what to expect from oversight consultants when they submit their schedules for approval. It...

CPM Schedule Specifications & Requirements: are they a waste of paper?

CPM Schedule Specifications & Requirements are generally found in CSI division 01 32 00 Construction Progress Documentation of a project manual or specifications, where they are routinely ignored...

Construction Completion Schedules for Accurate Closeout

  Nothing quite resembles the mad scramble contractors do to close out the final segments of their projects. By this time, the project schedule has likely been deprecated into a chaotic parallel...