4D BIM CPM Scheduling is a waste of time: here’s why.

4D BIM CPM Scheduling: not ready for prime-time

“The short answer is that there simply aren’t any extant Level III-IV 4D BIM risk-optimized or resource-loaded, apt CPM scheduling models with which to establish global parameters.

4D BIM CPM schedules can be generated from BIM models, but should they be?

That depends on who’s loading the parameters that 4D BIM uses to awkwardly splurt out dorky block diagrams that would make my Grampa chortle. But it also depends on what you’re objective is: if you just want to capture big picture, critical path and milestones, or staging and logistics, it’s a perfectly reasonable exploit. If you want to deep dive, you’re going to have to go for a deep-thought think tank of engineers and programmers. This is no longer a tenable option.

4D BIM is no longer a tenable option because 1) the models are unreliable; and 2) the cost of resources required to generate a risk optimized BIM model are prohibitive.

4D BIM CPM Scheduling

“Why? -hey don’t blame the platform.

4D BIM – Downright dowdy?

I am referring not so much to the logistics rendering, which has clear and rewarding benefits, as I am the wee bar chart below it. I don’t knock the Level I and II overviews, or specialty work that engineers have (too) painstakingly rendered from 4D BIM, but frankly they have better things to do.

There are more clever examples available, as there are 4D BIM hawkers praising its merits, but none of them incorporate resource loading or proper risk-optimizations, as such cannot be considered bona fide project control instruments any more than a bare duration-based CPM schedule. In point of fact, 4D BIM works in Pollyanna Perfect World Flowline theory, where there are 100% optimal conditions.

“AE has enough work to do with clash detection duty: let professional project controls folks do their job, and quit taking their work away from them. You really don’t want it anyway.

That said, there’s nothing inherently wrong with 4D BIM output – the problem is the input it is given is invariably based on faulty data sets that facilitate inaccurate risk-scenarios.

4D BIM CPM Scheduling

‘Doh!’

The likelihood of a builder following AE’s 4D BIM bar chart or animation for anything other than a general Level I reference is pretty miniscule. They will continue to pursue whatever CPM scheduling program they have been going with. Not for nothing, the BIM platform is not inexpensive, requires annual licenses, operators, and training and retraining for the operators. As a result, 4D BIM has yet to gain serious attention from the building community, and not been tried and true:

  1. Best practice dictates that any such 4D BIM CPM schedule should have all inputs, and inputs from all critical and near-critical path resources, i.e., contractors, vendors; even CPM schedulers. This is the exception rather than the rule of thumb for conflicts of interest, and conflicts in a general sense – another reason for lack of adoption.
  2. If AEs are generating 4D BIM schedules, perhaps it would be incumbent on them to share their work with the builder for his input, but I’d wager most would be risk averse to ‘tipping their hand’ in this fashion.
  3. It’s counterintuitive to let AEs lacking project control training unilaterally set the parameters for 4D BIM CPM schedule models: would you ask a sheet-metal worker with no mechanical drawing background to design a building in AutoCadd

4D BIM CPM Scheduling

“since you asked, the WBS in the status quo looks like it might have more to it than the eye candy on the right.

If we assume that the AE knowledge-base vacuum is generating 4D BIM CPM schedules, than what data set are the parameters based on?

‘It beats the heck out of me, and would befuddle any builder: I’ve never seen a builder use one. Most builders wouldn’t dream of building a Level II or IV detailed schedule from a 4D BIM animation- they regard as an exercise in futility.

Here’s a news bulletin: for the most part, AEs don’t really give a rat’s rear about 4D BIM CPM scheduling anymore than they do 5D BIM cost, save for a few technocrats, and why should they? Their certification requires no field internship, and neither estimating, nor resource-loaded scheduling, much less risk-optimized. As I’ve pointed out, neither do the Clueless Emperor CFOs and COOs making executive decisions in which they likewise have no more training than a chimpanzee.

“in other words, like an undefeated prize fighter who’s never taken a real punch, or gone over 5 rounds

So I rephrase: “4D BIM is a waste of time in its present level of deployment, implementation, and level of exactitude. 4D BIM lacks sufficient intuitive user interface mechanisms for ready adoption, and it is a considerable investment. Even if it did, a duration based logic baseline sans resource-loaded activities, will prove resistant to risk-assessments down the line.

“which is why so few schedulers get invited to the clandestine risk-register workshops.

With 4D BIM, it’s the old saw, literally, “that no structure can be built on weak foundations,” foundations being 4D BIM’s weak suit. AE baselines will invariably be defective from their point of conception onward. All of this means that 4D BIM, chronically a mainstream failure is ripe for disruption, and that disruption will be AI (artificial intelligence), i.e., AI CPM scheduling. Just like 4D BIM, parameters are set interactively. A white-paper on that subject is forthcoming, with an abstract in this space, and link to the full-paper. 

 

Archives: 2014 - 2024

Resource Loaded CPM Scheduling Strategies

Resource loaded CPM scheduling pertains to developing schedules based on activity durations predicated on production rates and constraints of available personnel or resources. Many project...

On the Adoption of AI Construction Scheduling Platforms

Recently, there have been some exciting developments in the field of AI construction scheduling platforms – such as the generative  “optioneering” platform offered by Alice Technologies*: the...

The Politics of CPM Scheduling

I think of politics in CPM scheduling primarily as an apt euphemism for sleight of hand reporting and representation of what contractors are either incapable of, or unwilling to give, accurate and...

Construction Disruption Claims & How to Optimize Them

In comparison to delay claims, construction disruption claims are a slippery slope when it comes time to make a claim. That’s because delays have finite start and end dates, where there is no work...

MEP Coordination Strategies

It’s been almost 10 years since I published my 4 part series on MEP coordination, and I thought “what better way to commemorate the occasion than with an update.” In that time a lot has changed and a...

CPM Schedule Oversight Best Strategies

CPM schedule oversight is a concern of both contractors and stakeholders.  Contractors should know what to expect from oversight consultants when they submit their schedules for approval. It...

CPM Schedule Specifications & Requirements: are they a waste of paper?

CPM Schedule Specifications & Requirements are generally found in CSI division 01 32 00 Construction Progress Documentation of a project manual or specifications, where they are routinely ignored...

Construction Completion Schedules for Accurate Closeout

  Nothing quite resembles the mad scramble contractors do to close out the final segments of their projects. By this time, the project schedule has likely been deprecated into a chaotic parallel...

Construction Bid Schedules: What They Are and Why Contractors Should Use Them

In requests for pricing (RFPs) or invitations for bids (ITBs) there are a number of requests or requirements that typically fall under the radar. One such is a seldom observed request generally known...